The
Elysator to be mounted as shown on the illustration, in a
by-pass position preferably over the main pumps, discharge
line to be connected to the lower half (inlet) and suction
line to upper half outlet. The inlet/outlet not in use is to
be plugged (only on type15- 100). The water flow to be
adjusted with the regulating valve after the flowmeter, while
the ball valve on the inlet remains full open. Pipes to be of
mild steel (galvanized pipes is not permitted) and with
diameter not less than 1” Elysator to be installed as close
as possible to the connection point, and as low as possible in
the system. Remember drain. Be sure that the when mounting the
Elysator to the deck, there is sufficient height above the
Elysator. (only for type 15-260) So there is space to lift up
the flange with the anode for cleaning overhaul etc.
|
|